Crome Constable Development Summary
Good afternoon All,
Please see the below summary of progress on site for March:
Up and coming works this month (See below Phase Plan for reference)
Phase one :
Screed completion
Plaster boarding and skimming to commence
Bricklayer to houses complete
Scaffolds to be dropped
External works to begin to front and back gardens.
Phase 2
Superstructure block and brickwork to begin
Precast plank installation to first floor.
Other works
Deep drainage works to begin on constable road
Gulley connection work to begin back end of April. (in line with road closure dates).