Update from Abri re: Shackleton Heights, Lockleaze

Hello all,

Please see the below summary of progress on site for April

Up and coming works this month

  • The last scaffolds will be down by end on play Monday 25th.

  • Boarding and skimming is ongoing within the plots now

  • Phase 2 first floor hollow core planks are due to go on first week of may.

  • External works are beginning to the frontages oof phase one (kerbs , stoning up for slabs.

  • Topsoiling to gardens

  • Fencing works to start next week